October 29, 2026
When bids opened on September 17, 2026, a Hampton contractor came in lowest on rebuilding the stone seawalls under three stretches of Route 1A. The state's approved bid tabulation for project 42312 lists William P. Davis Excavation LLC as "Awarded To" at $21,698,000, with a completion date of May 19, 2028.
For anyone who drives Ocean Boulevard, the bigger news is how small this first package is. These three stretches cover about 20 percent of a coastline project that NHDOT has split into 14 sections, and the state has already set advertising dates for the rest, one package each August through 2030. This winter's work zone is the first piece of a sequence that runs for years.
NHDOT's July 2025 public informational presentation names the three priority sections and ties each one to a landmark you already know.
| Section | Where it is | Length of roadway |
|---|---|---|
| Section 7 | Philbrick's Beach, south of The Beach Club and South Road, Rye | 959 feet |
| Section 10 | Bass Beach, south of Causeway Road, on the Rye/North Hampton line | 1,230 feet |
| Section 13 | Across from Fuller Gardens at Fox Hill Point, North Hampton | 1,020 feet |
That adds up to 3,209 feet out of a total project length of 16,814 feet. These sections went first because they won funding first. The structures were damaged in the nor'easters of January through March 2018, FEMA issued inspection findings that November, and in April 2024 NHDOT received a federal PROTECT grant aimed specifically at Sections 7, 10 and 13. Design started in October 2024.
The plans keep the walls where they are now. The presentation says the work will maintain the 1978 footprint and existing beach access, and will keep the pedestrian walkways and trails from the 1978 records where feasible. North Hampton's project page adds that the job includes ADA-compliant sidewalks, with a municipal maintenance agreement still under discussion.
Before bidding, NHDOT's September 2026 advertising schedule put the estimated contract amount at $26,195,300. The low bid came in about $4.5 million under that. It was also tight at the top of the field:
The top two bids were about $134,000 apart on a job worth more than $21 million. The low bidder's mailing address is a P.O. box in Hampton, a few miles south of the work. The award-date field on the tabulation is still blank. As of this week, NHDOT's project page still lists the status as "Design."
Since the walls hold up the road, rebuilding them means taking over part of the road. The contract is set up to keep that disruption out of summer.
At the Rye Select Board's June 8, 2026 meeting, DPW Director Jason Rucker told the Board that DOT would replace one revetment this winter and two more next winter. The Board approved a temporary road closure so crews would have a staging area for workers and equipment. According to the June 8 minutes, a message board will give residents "plenty of notice" before the closure. The town has not announced which of the three sections goes first.
North Hampton's Route 1A revetment page lists the anticipated construction conditions:
The first package's schedule lines up with that window. NHDOT lists its construction as running from winter 2026/2027 to spring 2028. The state has published advertising dates for the later packages but no construction or traffic schedules yet.
NHDOT's advertising schedule for the whole series reads like a calendar for the rest of the decade:
All 14 sections together cover 3.2 miles of coastline between Odiorne Point and Little Boars Head. The longest single piece is Section 6, at 3,806 feet, and it is next in line. The 2030 package is a different kind of job. Those five sections are mortar rubble masonry walls. The rest are shale pile, and most have stone revetment facing.
These are advertising dates set in a July 2025 presentation. Funding or design can move them. So far, the first package has stayed close to plan. The presentation set its advertising date for August 11, 2026. The September schedule shows August 18, and bids opened less than a month after that.
If you walk the shore at the north end of this stretch, the Odiorne Point fall schedule is already its own patchwork. The later phases will reach that end of the road.
The seawall contract isn't the only state or town job lined up along Rye's shore.
The culvert on Route 1A. NHDOT project 43002 replaces a 4-foot by 5.5-foot culvert with stone walls and a concrete deck. The state's information report puts the site just north of Locke Road. Bids opened October 8, 2026, and the completion date is October 15, 2027. The estimated contract amount is $1,404,900. At the June 8 meeting, an NHDOT representative described the culvert as being at the corner of Route 1A and Harbor Road. The four-sided box will become a three-sided one, which means extra foundation work and a three-week shutdown of the road. The Board said it had no issue with the closure as long as the work finished before the summer season. The minutes gave a spring 2026 window, starting after April 2 and finishing by the Friday before Memorial Day. That window has passed. NHDOT's later bid documents, with bids opening in October 2026 and completion due in October 2027, are the more recent schedule, and they do not give a start date.
The Harbor Road Bridge. At its August 24, 2026 meeting, the Select Board agreed to go ahead with the concrete replacement scope submitted to FEMA, described as 50 feet wide with a 75-year life expectancy. Earlier minutes from April put the FEMA submission at an estimated $1,491,950. Those minutes describe the concrete option as potentially FEMA-funded on a 75/25 split and say the pedestrian walkway is not eligible for FEMA funding. Hoyle, Tanner and Associates is the design consultant. The town expects more contract amendments as design and implementation continue.
The library calendar has a related date coming up. Rye DPW is holding an abutters meeting on the Harbor Road seawall easement survey on Tuesday, November 10, from 5 to 6 p.m. in the Community Meeting Room at Rye Public Library, 581 Washington Road.
One change people were watching for is off the table for now. After a months-long study commissioned by the town, the Select Board decided against metered parking along the oceanfront. The Portsmouth Herald reported on October 1 that Chair Howard Kalet said at the Board's September 28 meeting, "At this point in time, we have no plans to progress paid parking." According to the town's minutes, the Board had no plans to put it on the 2027 warrant either. The study did leave a mark. Its sight-distance recommendations at intersections led to some spaces being removed in the amended parking ordinance.
That leaves Ocean Boulevard's summer the same as before. The first contract's work is set for the off-peak months, and one section starts this winter at Philbrick's Beach, Bass Beach or Fox Hill Point. When the message board goes up, it will say which one. Our North Hampton and Rye neighborhood guides cover the towns on either end of the work.
If you own along Ocean Boulevard and wonder how a multi-year work schedule might affect a sale or purchase you're planning, Emil and Jackie at SellingTheSeacoast follow these timelines closely and can give you a clear, local read on timing. Start with a free home valuation.