October 8, 2026
"Create a canvas that is functional, nice to look at, but also very changeable." That is how Dave Desfosses, a longtime project manager in Portsmouth's Department of Public Works, described the city's goal for the Vaughan Mall in an NHPR story this summer. The line was about the walkway between Congress and Hanover. It also fits the street the walkway opens onto. Barriers have stood on upper Congress Street in some form since last winter, and the stretch now changes week to week.
New brick has gone down there since mid-September. The street looks close to done, but the city's own project page shows something else. This is the second part of Phase 1 in a three-phase project, and most of the work ahead sits a block or two away.
Upper Congress Street is part of the Fleet Street Area sewer separation. The city lists it as required under its Long Term Control Plan and Supplemental Compliance Plan. Along with the pipes, the project calls for full streetscape rework and pedestrian improvements. The city has laid out the order:
Phase 1 started inside the Vaughan Mall. The city began emergency replacement of sewer, stormwater and water lines there on September 2, 2025, because the old sewer line was failing. The plan was to put down temporary asphalt for the winter once the pipes were done. Then the crews moved to Congress Street. That segment replaces sewer, water and stormwater lines from Maplewood Avenue to about 100 feet east of the Fleet Street intersection.
The city chose to dig over the winter on purpose. It wanted the major utility work, and the worst disruption for businesses, finished in the cold months, leaving roadway and sidewalk restoration for later. So the spring brought rolling Fleet Street closures. In April, depending on the day's work, Fleet was closed from Porter to Congress or from Hanover to Congress, and normal traffic returned at the end of each workday. The city reported the utility and roadway work finished and the road open by June 13, 2026. Final paving and sidewalk restoration were left for fall.
The brick work happening now is that restoration. It ends the Congress Street segment. Maplewood Avenue and Fleet Street, Phases 2 and 3, have not started.
On September 14, crews started on the sidewalk in front of the Worth Building, near the corner of Congress and Maplewood. They are working down the Vaughan Mall side toward Fleet Street. Each section follows the same steps. The old sidewalk comes out. Curbs and light posts get raised. The subgrade is leveled. Then the new brick goes in, which the city describes as "less slippery."
The city's ground rules for the work zone:
On the street, that means a closed sidewalk at 2 p.m. on a Tuesday may be fully open by Saturday morning. The September 21 update had Congress down to one lane in front of the Worth Building for curb setting and brick laying. In the September 28 update, crews were still regrading sidewalks, setting brick and moving light poles, with the street again at one lane. Both updates said businesses would keep regular hours and that pedestrians should follow the flaggers.
Cranes Bistro opened at the corner where the brick work started and where the Vaughan Mall meets Congress. It's Julian Armstrong's fourth restaurant in Portsmouth or neighboring Kittery. He opened Anju Noodle Bar and The Wallingford Dram in Kittery in 2014, and The Wilder on nearby Fleet Street in 2017. The menu draws on Parisian cooking and North Atlantic seafood, including rotisserie chicken and steak au poivre. There's a long list of wines and beers from around the world, plus indoor and outdoor seating. Armstrong told the Detroit Free Press the project belongs to his "quiet dad era" and called it "a little more thoughtful, a little more curated."
Cranes started with a limited-reservations opening on September 24. It's now taking bookings on Resy, where it already has diner reviews.
Longtime locals may remember the address by its earlier tenants. The Worth Plaza unit was The District from July 2011 to October 2023. After that it was a restaurant and taproom from Litherman's Brewing Company and 603 Bar-B-Q, two Concord businesses that opened together in fall 2023. Armstrong bought the building in March for $1.785 million with Cranes already in mind. So he bought the building in the middle of the utility dig outside its door and opened the restaurant just as the new sidewalk reached it.
Down the mall, Lovebirds Donuts is still at 33 Vaughan Mall, and its website lists hours Wednesday through Monday. On a weekday morning, the walk from the doughnut counter to the Congress Street corner now crosses the newest brick in town.
The Vaughan Mall is next, but it's a separate project with its own schedule. The city's project page now lists the mall as "starting the restoration process" and notes that the sewer separation has moved on to Congress Street. The landscape plan presented July 22, 2026 calls for shade structures, more lighting, spots for public art including Italian light art, benches and a raised stage. It keeps the existing crabapple and honey locust trees. The mall has already given up some trees. The 2025 utility plan removed six trees from its center and kept four next to the parking lot. As Desfosses put it, "the less programming we had in the Vaughan Mall, the better off we were."
Here's the full Phase 1 schedule:
| Date | Milestone |
|---|---|
| September 2, 2025 | Utility replacement begins in the Vaughan Mall |
| December 9, 2025 | Public information meeting on Congress Street |
| June 13, 2026 | Congress Street utility and roadway work finished, road reopened |
| September 14, 2026 | Sidewalk restoration starts at the Worth Building |
| September 24, 2026 | Cranes Bistro opens with limited reservations |
| October–November 2026 | Vaughan Mall landscape work goes out to bid |
| December 18, 2026 | Final completion target set at the December 2025 meeting |
| Spring 2027 | Vaughan Mall landscape renovation |
Treat December 18 as the original target. The December 2025 presentation listed it as final completion, along with final paving and lane restriping. The city's September 28 update reported sidewalk work still in progress and didn't repeat the date. If the brick keeps moving about a block a week, paving and restriping should be the last visible steps on Congress before Phase 2 heads down Maplewood Avenue.
Downtown keeps a full calendar through the work. The 24th New Hampshire Film Festival runs October 15 through 18 at venues across downtown and shows more than 100 films. Weekend screenings fall on days the city has promised no sidewalk work.
The Illuminated Holiday Parade and Tree Lighting is set for Saturday, December 5. The Market Square tree lighting runs from 5 to 5:30 p.m., and the parade steps off at 6 p.m. Parade applications are due November 23. Online registration opened October 1. That's 13 days before the original Congress Street completion target.
The city posts weekly Congress Street updates on its project page, with an option to subscribe to alerts. It's the most reliable way to see which block the crews are on before you head downtown. You can find more downtown context in our Portsmouth neighborhood guide and our earlier post on the weekly clock downtown runs on in August.
If you own a condo or building near upper Congress, the Vaughan Mall or Fleet Street, you're living with these phases on your block. When you want to know how the finished streetscape and the work still ahead fit into your home's value, Emil Uliano and Jackie Mee can put together a free home valuation built on what's happening on your street.